Avery Chen <po-4390@mail.clearpo.com>
PO 4390
Please confirm PO-4390 for the 304 sheet and angle. Dock is receiving on weekdays, 7a–3p.
PO-4390.pdf
Thread
Northline Metals
Please confirm PO-4390 for the 304 sheet and angle. Dock is receiving on weekdays, 7a–3p.
Acknowledged. Promised dock date 12 Nov. Material certs will ship with the skid.
Mill slot slipped. We cannot hit 12 Nov. Revised ship week of 1 Dec. Sorry for the slip — certs are already cut.
Receiving can take a partial if the angle shows up ahead of the sheet.